Here is an outline for projects and potential funding for the next 6 years for Nonotuck Park upgrades. The consultants have outline the costs and the needs as submitted below. The projects outlined will update the aging pool infrastructure, add new features, provide ADA improvements and create more accessibility throughout the heart of Nonotuck Park.
Phase I - Pool upgrades BETA Budget $777,105 NAC Budget $426,000 $1,203,105.00
Funding Sources: PARC Grant $400,000 (68% of project cost) LWCF Grant Matching up to $750,000 CPA/CITY $190,000 PARC Grant 32% CPA/CITY $307,500 LWCF Match
2-3 years from funding to completion
Phase II - ADA Playground BETA Budget $758,821 Funding Sources: MOD ADA Project Grant up to $250,000 CPA Funds $250,000 CITY/State Earmark $258,821
Years 3&4 funding to completion
Phase III - ADA Pathways and Connectivity, Bioretention Area and Planting, Bike racks, Signage etc.... BETA Budget $451,591
Potential Funding Sources: Block Grant
State Grant CPA/City Match
Years 5&6 funding to completion