Nonotuck Park Open House                                                                                                                                                                                            June 27, 2022                                                                                                                                                                                                                                                    4:00 – 5:00 at Nonotuck Park Pool Area

Nonotuck Park Pool upgrades, ADA Playground and ADA Improvements.

Here is an outline for projects and potential funding for the next 6 years for Nonotuck Park upgrades. The consultants have outline the costs and the needs as submitted below. The projects outlined will update the aging pool infrastructure, add new features, provide ADA improvements and create more accessibility throughout the heart of Nonotuck Park.

Phase I - Pool upgrades                                                                                                                                                                                                           BETA Budget $777,105                                                                                                                                                                                                                                     NAC Budget $426,000                                                                                                                                                                                                                                       $1,203,105.00

Funding Sources: PARC Grant $400,000 (68% of project cost)                                                                                                                                              LWCF Grant Matching up to $750,000                                                                                                                                                                                                           CPA/CITY $190,000 PARC Grant 32%                                                                                                                                                                                                             CPA/CITY $307,500 LWCF Match

2-3 years from funding to completion

Phase II - ADA Playground                                                                                                                                                                                                                    BETA Budget $758,821                                                                                                                                                                                                                     Funding Sources: MOD ADA Project Grant up to $250,000                                                                                                                                                                                                        CPA Funds $250,000                                                                                                                                                                                                                                          CITY/State Earmark $258,821

Years 3&4 funding to completion

Phase III - ADA Pathways and Connectivity, Bioretention Area and Planting, Bike racks, Signage etc....                                                                                     BETA Budget $451,591

Potential Funding Sources: Block Grant

 State Grant    CPA/City Match

Years 5&6 funding to completion