See most recent Project Impact table to left. Traffic signal and RRFB work this week. Gas main relocation east side lower Union at Cottage.
Project Update - Sept 25-29
See most recent Project Impact table to left. Drainage work continues this week.
Project Update - Sept 18-22
See most recent Project Impact table to left. Drainage work continues this week.
Project Update - July 24-28
See most recent Project Impact table to left. Water work continues this week.
June 26-30 2023.
Ludlow Construction will be installing drainage pipeline and structures on Union Street this week between Liberty and High Street. See Table left for details. All users should expect delays.
July 26, 2022 - Press Release
The Union Street Reconstruction project was awarded to Ludlow Construction on April 27, 2022 by MassDOT. A "Notice to Proceed" with construction activities was issued to Ludlow Construction on May 17, 2022. They are required to complete the project by October 3, 2025. MassDOT personnel will be responsible for daily project management once work commences.
Ludlow Construction is progressing on project submittals, and utility agreements are being implemented. This summer, test pits for utility location confirmation are planned to allow for electric and gas relocations to begin later this summer and fall. Substantial construction activities could be underway this fall, provided no further supply chain or contractor delays exist.
The City of Easthampton will provide another project update in two weeks once the approved DOT schedule is received.
MassDOT project information can be found here: Projects (state.ma.us)