[ARCHIVED] Cherry Street Construction Scheduled to Begin

Easthampton Massachusetts

The general contractor for the Cherry Street construction project (Morais Concrete Services) will begin mobilization (i.e. bringing construction materials and equipment to the project area) starting next Monday, 8/22/22. They will also begin installation of the erosion & sedimentation controls and other prep work. We expect that Morais will then follow with the start of the underground utility work beginning around 9/1/22.